In September, drivers headed north on Highway 71 were sent around the intersection with Paul Bunyan Drive NW. The detour used Hannah Avenue and Anne Street, with two temporary compact roundabouts set on Hannah at 30th Street and at Anne Street to keep cars moving. MnDOT expected it to last about two weeks. By Sept. 23 the detour had been lifted.
Those two weeks were a preview of next summer. MnDOT's 2027 plan closes Highway 197 at Middle School Drive, and the detour it has named runs on the same two streets: Hannah Avenue and Anne Street.
The trucks are leaving for the winter, so this is a good week to see where the corridor stands. Most of what's finished sits on the side streets or at the corridor's west end. The two roundabouts left go on the highway itself, in the middle of the corridor.
Four of six roundabouts are already in the pavement
The full plan calls for six roundabouts between Highway 71 and Hannah Avenue. The City of Bemidji and MnDOT build them on separate schedules. Here's where each one stands as October ends:
- Middle School Drive at 23rd Street. This was the City's first roundabout. It finished in 2025.
- The Middle School Drive commercial entrance serving Target, Culver's and Dondelinger Chevrolet GMC. The City built it in 2026. The Bemidji Pioneer reported that the Middle School Drive stage wrapped up in July and the road was set to reopen by Monday, July 20.
- Hannah Avenue NW by Simonson's and Burger King. This is a compact roundabout, the City's third stage. Work started July 20, and access from Highway 197 onto Hannah was scheduled to stay closed through the end of August.
- The Menards entrance at Gillett Drive. This is MnDOT's 2026 piece, and it replaced the old signalized intersection. The north leg opened by Oct. 8.
- Highway 197 at Middle School Drive. MnDOT, 2027.
- Highway 197 at Hannah Avenue. MnDOT, 2027.
The first three are on side streets, where cars come off the highway and into the parking lots. The fourth sits at the corridor's west end. The last two go right where the highway crosses Middle School Drive and Hannah Avenue.
Why the order came out this way
None of this was planned as a two-year job. The Bemidji Pioneer reported that the project was first set to finish entirely in 2026, until a federal funding freeze stopped MnDOT's share. Lakeland PBS reported that the work was then split into separate City and MnDOT projects. The Bemidji City Council approved a $4,351,818.40 bid from Reierson Construction Inc. for the City's share. City engineer Sam Anderson put the total cost of that piece at $5,730,490.68, paid from several sources. He also said the City's own share would be about $1.4 million.
The split is why the side streets came first. The City could build its roundabouts on Middle School Drive and Hannah Avenue without waiting on the highway. MnDOT started at the far west end, by Menards and the Highway 71 intersection, and left its two crossings in the middle of the corridor for 2027.
MnDOT has also given its reason for using roundabouts at all. Leslie Seitz, MnDOT District 2 public affairs coordinator, explained it to Lakeland PBS when work began in May:
"There are 32 different intersecting points at a stoplight versus eight intersecting points at a roundabout. So, 32 ways to get in a crash versus eight ways to get in a crash."
MnDOT's statewide roundabout page reports an 86 percent drop in fatal-crash rates and an 83 percent drop in serious-injury-crash rates at intersections converted to roundabouts. Those are Minnesota-wide results, not Bemidji figures.
What changed this fall, and what's still wrapping up
This year's work went faster than planned. On Sept. 3, KAXE reported MnDOT was ahead of schedule and expected to finish the 2026 season in early October. The Oct. 8 MnDOT update listed the final steps:
- Gillett Drive: the north leg of the new roundabout is open to traffic.
- Highway 71 and 197: permanent signals were being installed, and crews planned to remove the temporary signals early the following week, once the new ones were turned on.
- Snow fence: already up near Gillett Drive, with more going in along the north side of Highway 197.
- Cleanup: final cleanup was scheduled for the following week, closing out the season.
That snow fence is the first winter-specific piece of the new corridor. MnDOT keeps a page on its snow fence and anti-drifting work for anyone curious about the fencing going up along the north shoulder.
The bigger long-term change for anyone on foot or on a bike is the trail. The finished highway will have a 10-foot multi-use trail on both sides, plus corridor lighting and better turn lanes. Making room for it meant removing the wide center median that used to split the driving lanes. MnDOT's Aug. 26 update showed trail work underway on the south side and said it would connect to next year's work. It also described two-stage pedestrian crossings with a refuge island in the middle. For now the trail stops partway down the corridor. It won't run the full length until the 2027 stages are built.
On the City's side, lighting is changing hands. Lakeland PBS reported that Otter Tail Power will own, install and maintain metal light poles for the Hannah Avenue and Middle School Drive work for a monthly fee paid by the City. Anderson said the arrangement also adds lighting on Conifer Avenue and on Hannah Avenue from the highway up to Anne Street.
The 2027 closure follows a route you already know
This is where September pays off. MnDOT has laid out the 2027 order in its updates:
- Restrictions lift for the season and crews come back.
- Stage 2: Highway 197 closes at Middle School Drive while that roundabout is built. Traffic detours over Hannah Avenue and Anne Street.
- Stage 3: once Middle School Drive is done, work moves to Hannah Avenue. That roundabout is built half at a time, with traffic still moving through.
- The season runs about June through October, like 2026.
That puts the full highway closure at the start of the 2027 season, at Middle School Drive, the street that leads to the new Target and Culver's entrance roundabout. Hannah Avenue carries the detour, and it already has its new compact roundabout by Simonson's and Burger King. Later in the season, the Hannah Avenue work stays open to traffic.
MnDOT hasn't said how long the Middle School Drive closure will last. It says it will hold a public meeting in the spring with a detailed schedule. During the 2026 season, MnDOT staff held a weekly public meeting on Wednesdays at 10 a.m. at MnDOT Headquarters, 3920 Hwy 2 W. The Hwy 197 project page has project details, detour maps and a sign-up for the weekly email updates.
Until crews return next summer, the corridor is as finished as it will be for a while. The Menards roundabout, the Gillett Drive realignment and the new Highway 71 signals are what you'll drive all winter.